KBA Holds Topping-out Ceremony for New Foundry at Press Plant
Facebook
Facebook
Twitter
Twitter
LinkedIn
LinkedIn
Email
Email
0 Comments
Comments
1,339 cubic metres of concrete
In just six months, a new shell was built around the existing 656-ft.-long production hall while production continued, with virtually no interruptions, and the old hall demolished. Special cranes were used to position 235 concrete parts with millimeter precision. The outer supports for two crane rails at different heights each weighed up to 56 tons and had to be inserted through the roof of the existing hall.