Having the Right Tools
Another challenge was estimating the most efficient layout and job plan for a project that included 50 different products, in multiple versions, across eight or nine different forms. "Planning combo jobs used to be a two-hour chore," Sita says. "Now, with CSV data import and the new auto plan tool, we have a good layout in about 20 minutes."